Infrastructure Renewal in Rockcliffe

Road, watermain reconstruction and sewer separation works are underway in parts of Rockcliffe. The works have been undertaken in two phases.

Phase “A” includes Hillsdale, Cloverdale, Northcote and Buena Vista (east of Acacia). This work is scheduled to completed to base course asphalt before winter. Landscaping and finishing works will be completed next spring.

Phase “B” includes Crescent plus Hillcrest and Thorold (both east of Springfield). Initially it was expected that this entire phase would likely begin 2003. Works have progressed well enough to allow for a portion of this phase to start this fall – i.e. Hillcrest and that portion of Crescent from Hillcrest to Buena Vista. Again this portion will be completed to base course asphalt before winter. The remainder of this phase will most likely only begin in the spring of 2003. As well, landscaping and finishing works will be completed in 2003.

At the start of these works, the contractor had requested an amendment to the hours during which construction activity would be allowed in order to minimize the time that streets would be disrupted. I consulted both the community association and the residents on the affected streets. In the event, the majority were in favour of having the pain and inconvenience over as soon as possible so the working hours were extended by one hour at each end of the day - i.e. from 7:00 a.m. to 7:00 p.m., Monday to Friday.

Councillor Jacques Legendre
I can be contacted by telephone at 580-2483, by fax at 580-2523 or by email at jacques.legendre@city.ottawa.on.ca
Visit your web site at www.rideau-rockcliffe.com

 

RETOUR À L'INDEX

 

 

 

 

 



MESSAGE DE JACQUES

Conseiller Legendre est heureux de vous souhaiter la bienvenue à son site web. 


CONSULTATION RIDEAU-ROCKCLIFFE

 

Rapport à Consultation Rideau-Rockcliffe (anciennement connu sous le nom Conseil de Quartier). 


Rapport annuel