MANOR PARK CHRONICLE

SEPTEMBER 2003

Birch Avenue Rehabilitation Project

Manor Park residents will know that Birch Street is to be completely rehabilitated this year. The works will involve the underground storm and sanitary sewers, the water main services as well as replacing the roadbed. The lighting along the road will be addressed as part of the project, but more on that later. It is also necessary that a sidewalk be constructed to bring this street, which is a residential collector carrying regular bus service in both directions, up to the standards required of such roads.

An initial public forum was held at the school on April 17 to discuss:
1- The preliminary designs and the sidewalk options,
2- Any concerns with staff,
3- The community’s comments and suggestions,
4- The proposed temporary rerouting of Bus # 7.

Initially, city staff was proposing to maintain the road width, currently averaging 9.5 metres, and adding a standard 2 metre sidewalk. There was to be no land expropriation, as there exists more than enough road allowance to accommodate the required facilities. Staff explained that the west side of Birch was the more suitable location for a sidewalk. There were far fewer trees threatened (if any) on that side. As well, there are underground pipes on the east side that militate against a sidewalk at that location. Residents requested that an option of incorporating a boulevard between the sidewalk and the roadway edge on the west side be examined – partly for snow storage but also as a way of distancing pedestrians from vehicular traffic. It was generally agreed that property owners immediately affected would be consulted on the matter. Bus service would divert through the community but only for the period of time necessary. The diversion from Birch would generally follow Dunvegan, Arundel and Merriman, accessing all or part of that corridor via Hemlock-Justin-Lonsdale or Eastbourne or Farnham as required.

A second meeting was held on June 17, primarily to review an updated corridor design and to discuss concerns specific to residents of Birch. The meeting discussed sidewalk positioning (i.e. boulevard or no boulevard), sidewalk material (i.e. tarmac or concrete) and sidewalk width. This meeting also considered whether the corridor should be centred on the existing roadway or whether the roadway edge should remain largely in place and the sidewalk added to the west side. The noise and potential vibrations caused by the buses was an important factor. Street lighting considerations were examined as well.

No clear consensus was reached that evening. As time was getting short to be able to finalize critical design elements and then issue the tender calls etc. for this season, I promised to discuss possible modifications with staff (within their delegated authority), incorporating as many of the features that seemed most desired and to seek approval from residents prior to proceeding. In the end, the vast majority of households on Birch accepted a proposal that featured:
1- A reduced road width from 9.5 metres to 9 metres;
2- A reduced western concrete sidewalk width of 1.65 metres;
3- A roadway edge on the east side at its current position.
Further deviations from standards over which city staff have delegated authority would have required Council approval (without any assurance of success for whatever was requested) and a year’s delay in project implementation. I believe that this design will serve the community at large very well for decades to come while offering the least possible undesirable consequences for the property owners along Birch. Work is expected to begin in early September. A reconstituted roadway, with an initial usable tarmac layer, should be in place prior to freeze-up. Finishing work, landscaping and lighting would follow in the spring.

One final aspect remains to be settled. The community will be consulted on the type of lighting fixture as well as on the type of light source. In this case there is more time to consider the options, as the installation of lighting will occur in the latter phases of the project. There will be a meeting in the community on this subject sometime in the fall or winter. There are three fixture options on the table, two of which (# 2 and # 3) will require Transportation Committee and Council approval. The options are:
1- 15 cobra head fixtures, located on the west side (as with the sidewalk, underground water and gas mains make it difficult to have the lamp-posts on the east side);
2- Approximately 20 coach style fixtures similar to those existing currently elsewhere in Manor Park (lighting level would not meet city standards); and,
3- The status quo providing a lighting level far below city standards.
Also, for each of the above options, there are two types of light source to consider – High Pressure Sodium (city standard; produces a yellow/orange light) and Metal Halide (not standard, requires Transportation Committee and Council approval; produces a white light and is more expensive both as to initial cost and on-going maintenance). No additional costs would be attributable to the residents if a decision were made to adopt a higher cost option, either for the type of fixture or the light source.

You may wish to consider these options and discuss them with your neighbours in advance of the public meeting. My office is always available should any questions arise.

A Truly Outstanding Effort!

Mr. & Mrs. Robertson, of our Cardinal Glen community, have shown all of us what can be achieved by way of diverting waste from our landfill. In April, the Ottawa Citizen carried their story, marking the first time in 3 years that this couple had put out even one bag of garbage! They have adopted the “reduction, reuse, recycling and composting of household materials” strategy extraordinarily effectively. Their efforts in helping to make the City of Ottawa a better environment in which to live were recently recognized by the City of Ottawa’s Transportation, Utilities and Public Works Department. Well done!


You can communicate with me at (please include a telephone number):
City of Ottawa
110 Laurier Avenue West
Ottawa ON K1P 1J1
Tel: 580-2483, Fax: 580-2523
E-mail: jacques.legendre@ottawa.ca
Web Site: www.rideau-rockcliffe.com


back to index

 

 

 

 

 



MESSAGE FROM JACQUES

Councillor Legendre is pleased to welcome you to his web site


CONSULTATION RIDEAU-ROCKCLIFFE

 

Report to Consultation Rideau-Rockcliffe (formerly known as the Ward Council).


Annual Report